Completed the Major Projects in last Ten years |
|||||||||
Sl.No |
Project Name |
Name of Employer/Client |
Description of the work |
Value of Contract (Lakhs) |
Contract No |
Date of Issue of Work order |
Stipulated date of completion |
Actual date of completion |
Remarks explaining reasons for Delay, if any |
1 |
MAC CRICKET STADIUM, CHENNAI |
THE TAMIL NADU CRICKET ASSOCIATION, M.A. CHIDAMBARAM STADIUM, VICTORIA HOSTEL ROAD, CHEPAUK, CHENNAI Ph: 044- 28544175 contact person : Mr. SHANKAR Contact No: 9940629908 |
LOI for Dismantling works M/s. TNCA Stadium Phase 2 & 2A |
135.00 |
Nill No./12-04-2010 |
12.04.2010 |
27.05.2010 |
24.05.2010 |
Work completed 3 days earlier on schedule |
2 |
MANTRI BLOSSOM, BANGALORE |
MANTRI GARDEN VIEW HOMES PVT.LTD, MANTRI HOUSE, #41, VITTAL MALLYA ROAD,BANGALORE-560001. Contact person: MR.MAHENDIRAN Contact no: +91-7259035044 |
Retofitting Works at Mantri centrium site, Bangalore-560001. |
277.31 |
WO/LALBAGH/43 |
28.06.2013 |
31.12.2013 |
20.01.2014 |
Delayed due to additional scope of works |
3 |
CPCL, MANALI, CHENNAI |
CHENNAI PETROLEUM CORPORATION LTD, #68, MANALI, CHENNAI-600 058. Contact Person: Mr.Manoj Contact No 044-25944000.(Civil projets) |
Protective Coating of CO Stack of PCC unit during Refinery-II shutdown in the month of October-2018 at CPCL, Manali |
6.12 |
25668278 |
06.10.2018 |
06.10.2018 |
06.10.2018 |
Completed as per schedule. |
4 |
CCTPL, CHENNAI |
ITD CEMNETATION LIMITED National Plastic building, A-Subash Road , Paranjape B Scheme , Vile Parle , (East) Mumabi- 400 057. Contact Person: Mr. SAGAR LIMAYE-9100775264 |
Repair works in Area -2 in CCTP |
37.60 |
A2-001-SC-44717DM-ITDCem-CCTL-2017 |
25.01.2018 |
24.02.2018 |
24.02.2018 |
Completed as per schedule. |
5 |
NIRMA SITE AT BHAVNAGAR |
NIRMA LIMITED Nirma House , Ashram Road, Ahmedabad- 380 009. Contact Person: DR PATEL -7574892502 |
Demolition of Chimney (121.0 m ) |
206.00 |
Y/8001003 DO 181000093 |
29.10.2018 |
30.04.2019 |
30.04.2019 |
Completed as per schedule. |
6 |
DP WORLD |
CHENNAI CONTAINER THERMAL PVT. LTD No.1, Administrative Office, Rajaji Salai, Chennai- 600 001. Contact Person: Mr.MURUGAN-9884306793 |
Wharf repair works |
403.89 |
LOA DT-24.04.2019 |
24.04.2018 |
15.08.2019 |
23.10.2019 |
Due to Non availability of work front |
7 |
Expansion of SMS3 & CRM 1 |
JSW STEEL LTD, VijayaNagar works, Vidyanagar PO, Toranagallu Village, Vidyanagar-583275, Ballari, Karnataka. Mr.Niladri Samanta - 9886479441 |
Foundation Modification Works |
330.25 |
PO NO: VJNR/P00033/C/ 4700083527 |
20.12.2019 |
20.06.2020 |
20.06.2020 |
Completed as per schedule. |
8 |
WDFC-15B, NARMADA RIVER, BHARUCH, GUJARAT |
LARSEN&TOUBRO LTD, MOUNT POONAMALLE ROAD, MANAPAKKAM, CHENNAI-600089. Contact Person: Mr.MATHUSOOTHANA RAO-7574847905 |
Dismantling of Collapsed RCC well in narmada river using under water cutting system. |
203.72 |
EC885WOD0000044/22-10-2020 |
22.10.2020 |
31.03.2021 |
31.03.2021 |
Completed as per schedule. |
9 |
NFC, HYDERABAD |
NUCLEAR FUEL COMPLEX, DEPARTMENT OF ATOMIC ENERGY OF INDIA, ECIL (PO), HYDERABAD-500062. Contact Person: Mr.NANDAKUMAR- +9140-27183169 |
Demolition of Old Chlorination plant & Existing Titanium Pilot Plant at NFC, Hyd |
19.75 |
NFC/CED/C-1435/391 |
11.08.2021 |
31.03.2022 |
31.03.2022 |
Completed before schedule |
10 |
CPCL'S CBR, NAGAPATTINAM |
BRIDGE AND ROOF CO. INDIA LTD, 4TH & 5TH FLOOR, KANKARIA CENTRE, 2/1, RUSSEL STREET, KOLKATA-700071. |
Carrying out Dismantling & Stacking of Equipments Works at Existing Facilities in CPCL's Cauvery basin Refinery at Nagapattinam |
775.74 |
B&R/PCD/71119/WO-DISMG.EQUIP/LC/151 DT:01-12-2021 |
1.12.2021 |
31.03.2022 |
31.03.2022 |
Completed as per schedule. |
11 |
CPCL'S CBR, NAGAPATTINAM |
BRIDGE AND ROOF CO. INDIA LTD, 4TH & 5TH FLOOR, KANKARIA CENTRE, 2/1, RUSSEL STREET, KOLKATA-700071. |
Carrying out Dismantling & Stacking of all concrete Buildings, Foundations, Fire proof materials, Refractory and its allied facilities works at Existing Facilities in CPCL's Cauvery basin Refinery at Nagapattinam |
309.99 |
B&R/PCD/71119/WO-CIVIL/LC/134 DT:12-11-2021 |
12.11.2021 |
31.03.2022 |
31.03.2022 |
Completed as per schedule. |